Adoption of extreme wind loading standards so the system could handle hurricane-force winds
Segmentation of feeder lines to reduce the number of customers affected by an outage
Development of a smart-grid assessment team to perform restoration replacement approaches immediately following a storm
Results:
Post-hurricane restoration time shortened from 18 days to 10 days
Result: $8 billion back into Florida’s economy
4.2 million customer interruptions avoided over six years from IntelliRupter® fault interrupters
8,500 interruptions avoided over four years from TripSaver II reclosers
When building a reliability-improvement program, it’s not simply one solution but several solutions that come together to make significant change. Extraordinary results come from a larger, multiple item strategy.
Ron Critelli, Senior Director of Power Delivery Engineering & Technical Services, Florida Power & Light Company
Video: See how FPL’s resilience plan helped its customers in the aftermath of Hurricane Irma.
Read the Full Case Study
Case Study
A Comprehensive Commitment Challenges Power Reliability's Status Quo
What grid upgrades did FPL make to shorten its hurricane restoration time by eight days?