Largest Wind Farm in Ontario Delivers Power on Schedule

S&C played an important role in the construction of Ontario’s largest operating wind farm – the 189-MW Prince I & II Wind Energy Project. For this project, S&C operated under an EPC contract with Mortenson Canada Ltd. for the wind farm collector systems, and Brookfield Power for the interconnect substations, switching substation, and transmission line. Despite a challenging environment, the wind farm was completed on time and on budget. This article from North American Windpower provides an overview of the challenges of this project. Download the complete article.

S&C also offers an array of products and services for wind energy applications, including the PureWave DSTATCOM® Distributed Static Compensator – which provides dynamic reactive power compensation for renewable energy, switching and protection equipment, and an array of services.